WeWork Office, Berlin

Berlin Final Project 1
Berlin Final Project 10
Location Berlin, Germany
Timescale 16 weeks
Client WSG

Premier Electrics delivered the full electrical installation of the 9-storey state-of-the-art WeWork offices in Berlin.

The 16-week programme involved a full electrical installation including power infrastructure, security, door access and data systems along with intelligent lighting and window blinds systems.